Kanpur Sewerage Profile


City_ Sewerage_ Profile _Kanpur
General Information
 Number of wards110
Area in Sq Km (Kanpur Nagar Nigam)260 sq Km
Population  (In Lakh)Year 20112774502
Year 2019Projected3113263
Total capacity in mld Required (Currently)468 MLD
Total capacity in mld Available
Operational409 MLD
Ready for operation43 MLD
Under Construction15 MLD
Gap Nil
Description of STPs and Sewerage Line Subtotal Detail
SN 1234567
Description
1Name of The STPJajmau-1Jajmau-2Jajmau-3Jajmau-4BingawanSajariBaniya purwa 
2Districts/Project area nameDistrict-1District-1District 1District 1District -2District -4District -3 
3Number of Wards Covered34 Nos.58 Nos.4 Nos.14 Nos. 
4Capacity (in mld)130527432104215429
5STP designed for the yearYear -2020Year -2020Year -2020Year-2040Year -2030Year -2050Year -2050 
6Current inflow in mld95-100 MLD4.5-05 MLD24-27 MLD145-155 MLD12-15 MLD 
7SPS/MPS details (Name & Capacity)1. SPS Nawabganj-15MLD     2.    SPS   RSPH – 45MLD  3. Parmat – 40 MLD
5. Muirmill – 6.5 MLD, 6. Guptar Ghat – 3.5 MLD, 7. Parmiya – 3.5 MLD, CSPS- 130 + 25 MLD
1. SPS  Munshipurwa- 67 MLD, 2. Rakhimandi- 100 MLD, 3. Halwa Khanda- 20 MLD 4. MPS- 200 MLD1. SPS  Chakeri -14MLD
2. SPS   Sanigawa- 14 MLD 3. MPS- 42 MLD
1. Lakhanpur – 05 MLD
2. MPS – 15 MLD
 
Sewerage Line Infrastructure Details
8Total Sewer Laying Length (in Km) required for full HH coverage of the STP project area (Main trunk line, and branch line)720.9240001744505,171
9Total Sewer Line Infrastructure available  (in Km) (A+B)61811798716
A)Sewer line already available618116211798716
B)Sewer line laid  under various STP projects00000
10Sewer line sanctioned (in Km) in various STP projects  (C+D)102.922044100223
CSewer line laying work completed ( in km)  in various STP projects against sanctioned310221041
DSewer line laying work ( in Km) under construction in various STP projects against sanctioned71.92202290182
11Gap in Sewerage Line Infrastructure (in Km) (8-9)03980132524232
12Available Sewerage Line infrastructure non functional/non operation   0
House Hold sewerage Connection Details
Total No of House Hold Connection Required (as per population projection for 2019)-2,54,000 2,54,000
13Number of total House Holds connection required under STP coverage area98,3941,84,91655110328462,83,310
14Number of Existing House Hold Connections as per ULB record65,9821,14,2752132360341,80,257
15Number HH Covered under sanctioned Projects (AMRUT)324125,71881462681238,130
16GAP in House Hold Connection Coverage (13-(14+15))064,92325,641064,923
 Gap Plan For Kanpur Sewerage Projects -Proposals already submitted for approval
1. DPR of District 2 Part-‘E’ (Proposed)
(Proposal submitted to NMCG)
Proposed Cost : Rs. 318.63 Cr.
Sewerage Network Proposed: 205 Km
Proposed Number of Sewer House Hold Connection: 7569 Nos.
Date of DPR submission: 16 August 2018
Current status: Revised/Modified DPR amounting to Rs. 322.38 Cr. has been submitted to NMCG after removing objections on dated 16.10.2018.

Have any Question or Comment?

Leave a Reply

Your email address will not be published. Required fields are marked *

Social Media Pages: Facebook Pagefacebook.com/cleangangasmcgupTwitter Pagetwitter.com/cleangangasmcgTwitter Pageinstagram.com/cleangangasmcgupFacebook PageYouTube